ePoint Medway; 40 days to go

With just 40 working days to the completion of ePoint’s fit out phase and first user implementations, we are welcoming more visits from customers, prospective customers and film crews.

Last week, during a break in some exceptionally bad weather, we were very pleased to host a camera crew from key build partner MiTek Mezzanine Systems (who have created 215,000 sq ft of additional work and storage at ePoint, with our cleverly designed 4 floor #mezzanine) to interview Steve Hicks, Contract Logistics Director North Europe for Noatum Logistics.

Despite the photos apparent calm, there are currently over 120 contractors inducted and working on-site at ePoint, so the film crews noise-cancelling sound system will have been working flat-out, to pick Steve’s voice from the surrounding cacophony!

ePoint’s progress remains on plan, with no construction days lost to COVID and just one contractor self-isolating. Risk mitigation steps have been taken, to further protect colleagues and contractors.

Weekly planning meetings have started with the first ePoint customers and the facility is welcoming visits from more potential users.